SUPPORT LIBERTY'S LAW!

Thursday, March 06, 2014

Roadwork continues in Milton.

Roadwork projects continue throughout the city in January.

ROADWORK

Please note: All dates on roadwork projects are estimates and are based on weather conditions. Any road closures will be sporadic and announced well in advance.

Ga. 140 at New Providence Road

In July, CMES, Inc. began intersection improvements at Ga. 140 (Arnold Mill Road) and New Providence Road. Plans include redirecting the intersection approach, adding turn lanes and installing a traffic light.

The Georgia Department of Transportation (GDOT) awarded the construction contract to CMES, Inc. in the amount of $1,161,626.92. The job is expected to last one year.

Ga. 372 at Providence Road/New Providence Road In August, Bartow Paving Company, Inc. began intersection improvements at Ga. 372 (Birmingham Highway) and Providence and New Providence Roads. Plans include redirecting the intersection approach and installing a roundabout.

GDOT awarded the construction contract to Bartow Paving Company, Inc. in the amount of $2,576,297.45. The job is expected to last 18 months.

Hopewell Road at Francis and Cogburn roads

In August, Baldwin Paving Company, Inc. also began intersection improvements at Hopewell Road at Cogburn and Francis roads. Plans include installing a roundabout.

The City of Milton awarded the construction contract to Baldwin Paving Company, Inc. in the amount of $786,606. The job is expected to last one year.

For more information on these projects, visit http://miltonintersectionprojects.com or contact Angie Kapijimpanga, citizen responder for the City of Milton, at 678-242-2562 or angie.kapijimpanga@cityofmiltonga.us.

No comments: